Duration
December 1995 – May 1998
Location
Melaka
Sg Udang, Melaka
Contract Sum
RM 35 Million
Client
Sajaya – Yong Nam JV
The Petronas Second Refinery, Plant II project in Sg Udang, Melaka, involved the construction of tank foundations, fire dike walls, and a treatment plant. This infrastructure was crucial for the operations of the refinery, particularly for the safe storage and management of hazardous materials like petroleum.
Pembinaan Thin Chai Sdn.Bhd collaborated with Sajaya - Yong Nam JV for the project. The construction took place from December 1995 to May 1998, with a total contract value of RM 35.0 million. This project likely contributed significantly to the expansion and enhancement of Petronas' refining capacity in the Sg Udang area of Melaka.