Duration

February 1995 -July 1995

Location

Selangor

North Port KlangTerminal 2nd Berth and Silo No.3, 

Contract Sum

RM 5.3 Million

Client

Sato Kogyo Co., Ltd

The Kedah Cement Sdn. Bhd. project at North Port Klang involved the construction of Terminal 2nd Berth and Silo No. 3. This project aimed to build a terminal, jetty, and silo to facilitate the handling and storage of cement or related materials. Pembinaan Thin Chai Sdn.Bhd collaborated with Sato Kogyo Co., Ltd for the project. The project was executed from February 1995 to July 1995, with a total contract value of RM 5.3 million. This infrastructure likely played a crucial role in supporting the logistics and transportation of cement products in the North Port Klang area.