Electrified Double Tracking Project Between Ipoh and Padang Besar
Electrified Double Tracking Project Between Ipoh and Padang Besar
GET IN TOUCH
Duration
Feb ’09- Aug ’11
Location
Ipoh and Padang Besar
Contract Sum
RM 3.2 Million
Client
MMC-Gamuda JV
The Electrified Double Tracking Project between Ipoh and Padang Besar in Perak Darul Ridzuan, Malaysia, included the construction and enhancement of Bridge RB 18 and RB 19, with a contract value of RM 3.2 Million. This critical infrastructure initiative, carried out by Pembinaan Thin Chai Sdn Bhd in partnership with MMC-Gamuda Joint Venture, spanned from February 2009 to August 2010. The primary objective was to facilitate the electrification and modernization of the railway line, thus improving rail transportation efficiency and connectivity in the region, thereby contributing to the overall development and transportation infrastructure of Perak Darul Ridzuan.